CET Bucharest West will be stopped for six hours on Wednesday, for the replacement of some gas detection sensors

CET Bucharest West will be stopped on schedule on Wednesday, between 8:00 a.m. and 2:00 p.m., for the replacement of some sensors in the gas turbine protection system, Electrocentrale București announced on Tuesday. The plant will be restarted at 14:00 and should return to optimal parameters by 16:00.

The sensors to be replaced detect possible gas leaks in the turbine compartment and are essential for the safe operation of the equipment.

The intervention cannot be carried out while the turbine is running, because the temperature in the compartment exceeds 100 degrees Celsius. The six-hour shutdown also includes time for controlled cooling of the facility.

“The six-hour interval is necessary for the controlled cooling of the equipment and the execution of the replacement work,” Elcen representatives explained.

The company stated that the intervention is strictly preventive. Postponing the work could cause turbine failure and an unscheduled shutdown of the plant for a longer period, with effects on heat and electricity production during the cold season.

“Delaying the replacement of these sensors could expose the equipment to major risks and could generate an unexpected stoppage of the turbine, which would lead to the unavailability of the plant for a longer period, with a significant impact on the supply of heat and electricity in the middle of the cold season,” the company’s statement reads.

The shutdown was scheduled during the day to avoid peak evening hours and the night time slot when outside temperatures are cooler.